What are the dimensions measured on a stakeholder grid?
A. Access and availability
B. Expertise and influence
C. Interest and power
D. Motive and opportunity
2. Which of the following is not a tool used to manage the stakeholder engagement?
A. Communication methods
B. Interpersonal skills
C. Management skills
D. Issue log
3. The primary purpose of the stakeholder register is:
A. To keep a list of all project stakeholders
B. To record stakeholder issues on the project
C.
To map functional requirements but to the originate in stakeholder
D. To serve as a project directory
4. The most important element in project success is:
A. Stakeholder satisfaction
B. How the product meets the requirements
C.
Overall product quality
D.
Overall project quality
5. Which of the following does not identify someone as a stakeholder during stakeholder analysis?
A. Someone who proposes a solution
B. Someone who creates a need
C.
Someone who is affected by the need
D. Someone who would be affected by the solution
6. Identified stakeholder needs should all be:
A. Addressed by the project product
B. Qualified
C. Ranked from greatest to least
D. Documented in the stakeholder management plan
7. Which of the following is not a classification of stakeholder engagement?
A.
Unaware
B. Resistant
C. Leading
D.
Participating
8.
Dave is working on a matrix where he is measuring the stakeholder
engagement on the project. What dimension would he likely to be
assessing and plotting?
A.
Power and interest to influence the project
B. Ability and urgency to influence the project
C.
Current and desired levels of interest
D.
Expertise and availability to engage with the project
9. Which of the following statements is false regarding stakeholders?
A. Stakeholders may have a positive or negative interest in the success of the project
B. All stakeholders should be identified before the project execution begins
C. Stakeholders may not be affected by the outcome but may perceive that they could be affected by the outcome
D. Stakeholders may be people, or organizations
10. Which of the following is true concerning work performance data and work performance information?
A.
Work performance data is used at the organizational level, while work performance information is used at the project-level
B. Work performance information is more useful than work performance data
C. Work performance data is collected from monitoring and controlling processes
D. Work performance information represents raw observations and measurements
===================================================================
ANSWERS.
1. C. When plotting stakeholder interest on a matrix, interest and influence, and sometimes involvement, are measured
2. D.
This may have looked hard, but it was not so difficult to reason out.
The issue log is the primary output of manage stakeholder engagement, so
it could not also be a tool. A, B, and C are all tools used in that
process
3. A. The stakeholder register is a list of the stakeholders with their assessment and classification as it relates to the project
4. A.
This one should have been easy given the topic of the quiz, but you may
well see questions like this on the PMP Exam. While all of the
elements are important, stakeholder satisfaction is the most important
5. B.
The term stakeholder is very broad and generally includes quite a few
groups. However, someone who creates a need is ambiguous enough to not
fit well within this list. There will always be people who create needs
or problems on your project, and that does not automatically qualify
them as a stakeholder.
6. C. Stakeholder needs
are to be ranked from greatest to least. This is key for determining
project priorities. “A” would be wonderful, but it is not realistic to
think that every need a stakeholder raises will be addressed by the
project. ”B” is not a bad answer, but by the time they are identified,
they are essentially qualified as stakeholders. ”D” may sound like a
good answer, but the stakeholder management plan is created before the
stakeholders have been identified.
7. D. The
five states of stakeholder engagement are Unaware, Resistant, Neutral,
Supportive, and Leading. “Participating” might seem to make sense, but
it is not a classification since the project manager does not typically
need to measure the engagement of team members participating on the
project.
8. C. The stakeholder engagement matrix plots the current and desired levels of engagement by stakeholders.
9. B.
If you missed this one, don’t feel bad. It is best to identify
stakeholders early, but the key to getting it right is the word “all”.
Many of them may not emerge until late in the project.
10. B.
WPI and WPD show up in Control Stakeholder Engagement. Remember that
work performance data is raw, while work performance information has
been analyzed and made more useful. “A” has no grounding in reality at
all, and “C” and “D” are opposite of the truth
======================================================================
In the stakeholder register the stakeholders
can be classified into the following.
a. Internal/external
b. Supporter
c. Neutral
d. All
of the above
2.
Influence/
Impact grid classify the stakeholder based on the following
a. Power
and Influence
b. Influence
and Impact
c. Power
and Urgency
d. Power
and Interest
3.
Which
of the following is not input to Identify Stakeholders process
a. Project
Management Plan
b. Project
Charter
c. Procurement Documents
d. Organizational
Process Assets
4.
Organizational
Process Assets that an influence the Identify stakeholder process include.
a. Stakeholder
register from the current project
b. Issue
log from previous projects
c. Stakeholder
register from Previous project
d. None
of the above
5.
The
engagement level of the stakeholders can be classified as
a. Unaware
b. Resistant
c. Neutral
d. All
of the above
6.
In a highway construction project the planning
was complete and execution was about to begin.
The villagers living in vicinity came out and stopped the execution.
They demanded a very high compensation that adversely impacted the budget and
timelines of the project. Which process from PMBOK would have helped in
preventing this problem from occurring?
a. Identify
Stakeholders
b. Plan
communication
c. Plan
Budget
d. Develop
Schedule
7.
Which
of the following processes do not use meetings as a tools and techniques?
a. Identify
Stakeholders
b. Plan
Stakeholder Management
c. Manage
Stakeholder Engagement
d. Control
Stakeholder Engagement
8.
Project
plan updates during Manage Stakeholder
Engagement Process can be due to
a. Change
in the scope baseline
b. Change
in the schedule baseline
c. Change
in the cost performance baseline
d. Replacement
of an ineffective communication method by a new method
9.
Which
of the following statement about the issue log is correct
a. The
Issue log contains Risks and is created during Manage Stakeholder Engagement
Process
b. The
Issue log contains Issues and is created during Plan Stakeholder Engagement
Process
c. The
Issue log contains Issues and Risks and is created during Control Stakeholder
Engagement process
d. The
Issue log is updates as new issues are
identified and current issues are resolved during Manage Stakeholder Engagement
Process
10. Which of the following
are output of Manage Stakeholder Engagement process
a. Project
Management Plan Updates
b. Organizational
Process Asset Update
c. Change
Request
d. All
of the above
11. Which of the following
is the process of monitoring overall project relationships and adjusting the
strategies and plans for engaging stakeholders?
a. Control
Stakeholder Engagement
b. Plan
Stakeholder Engagement
c. Manage
Stakeholder Engagement
d. Identify
Stakeholders
12. Work Performance Data
is input to which of the following
process
a. Control
Stakeholder Engagement
b. Plan
Stakeholder Engagement
c. Manage
Stakeholder Engagement
d. Identify
Stakeholders
13. Which of the following
processes is used to process the change requests generated from analysis of
project performance and interaction with the project stakeholders?
a. Control
Stakeholder Engagement
b. Perform
Integrated Change Control
c. Manage
Stakeholder Engagement
d. Plan
Stakeholder Engagement
14. Who of the following
are project stakeholders?
a. Someone
who thinks that they are impacted by the outcome of the project
b. Competitors
c. Team
members
d. Government
15. Fill in the blank
Projects stakeholders
are individuals, groups, or who may effect, be
affected by, or perceive themselves to be affected by a decision, activity, or
outcome of the project.
a. Team
b. Team
Members
c. Sponsors
d. Organization
16. The number of stakeholders
in a project depends upon
a. Size
of the Project
b. Type of the Project
c. Complexity of the Project
d. All
of the above
17. Project Charter is an
input in the Identify stakeholders process and it provides information related
to
a. Project
Budget
b. Major
Risk
c. Project
Timelines
d. Internal
and External parties related with the project
18. Which of the following
document provides guidance in managing stakeholder’s expectations?
a. Stakeholder
Register
b. Stakeholder
Management plan
c. Communication
Management Plan
d. Project
Management Plan
19. For a project that is a
result of a procurement activity, which of the following is a key stakeholder?
a. Suppliers
b. Parties
in the Contract
c. Competitors
d. Customers
20. Which of the following
are the contents of the Stakeholder Management Plan
a. Desired
and current engagement levels of key stakeholders
b. Identified
Interrelationship and Potential overlap between stakeholders
c. Stakeholder
communication requirements for the current phase
d. All
of the above
21. Which of the following
are true about activities related to the
process Manage Stakeholder Engagement
a. Engaging
stakeholders at appropriate project stages to obtain or confirm their continued
commitment to the success of the project
b. Clarifying
and resolving issues that have been identified
The
correct answers are:
a. a
& b
b. a
only
c. b
only
d. None
of the above
22. Which of the following
process has Interpersonal skills as a tools and techniques?
a. Identify
Stakeholders
b. Plan
Stakeholder Management
c. Manage
Stakeholder Engagement
d. Control
Stakeholder Engagement
23. Which document
provides the information related
to needs and techniques for communication among stakeholders
a. Project
Management Plan
b. Stakeholder
Register
c. Stakeholder
Management Plan
d. Communication
Plan
24. Percentage work
completed, technical performance measures , start and finish dates of scheduled
activities , number of change requests, number of defects , actual costs and
actual duration etc are included in
a. Work
Performance Information
b. Work
Performance Data
c. Performance
Reports
d. Forecasting
25. Which
of the following process uses Information Management System as a tool and
technique
a. Identify
Stakeholder
b. Plan Stakeholder Engagement
c. Manage
Stakeholder Engagement
d. Control
Stakeholder Engagement
1. d
2. b
3. a
4. c
5. d
6. a
7. c
8. d
9. d
10. d
11. a
12. a
13. b
14. c
15. d
16. d
17. d
18. c
19. b
20. d
21. a
22. c
23. a
24. b
25. d
=======================================================================